Tunneling Under Austin Protecting the Environment, and Preserving the Peace

$17.50 plus tax (Refund Policy)

Buy Article:

Abstract:

For over a decade, an existing 42-inch wastewater interceptor has plagued the Austin Water Utility (Utility) with higher than usual maintenance demands. Located in the Walnut Creek flow line, this interceptor is partially exposed with manholes rising several feet above the creek bed due to years of erosion. The interceptor suffers from external erosion and is victim to debris floating down the creek during rain events.

On two separate occasions, the Utility designed a new parallel interceptor to replace the existing one only to have the project halted by the public and local home owners' association. The environmental concerns, coupled with stream bank erosion and stabilization issues, made this project a heated debate for City residents. To further aggravate the situation, in 1999 the Utility was put under an Administrative Order by the U.S. Environmental Protection Agency (EPA) to eliminate sanitary sewer overflows in their wastewater conveyance system by December 31, 2007.

This project utilizes trenchless technology coupled with traditional construction methods to develop a variety of solutions – and ultimately the best solution for the project. It was imperative to keep the public impacts to a minimum and have the project substantially complete by the mandated date of the EPA's Administrative Order. The fast tract schedule mandated work in double shifts for at least a portion of the project and did not leave much time for changed or unforeseen conditions. Because of these specific project conditions, it was important to assure that the element of risk on the project was kept to a minimum and shared by the Utility and the Contractor. In order achieve this several items were incorporated into the project, and are listed below:

Differing Site Conditions Clause


Geotechnical Baseline Report


Disputes Review Board


Escrow Bid Documents


Pre-Construction Survey


Noise Abatement


Monitoring Ground Movement


A win-win for the Utility and the residents, this project won acceptance from the residents, minimized impacts to the community and the environment, and eliminated land acquisition requirements. The project began construction in June of 2004 and the tunneling operation was complete in November of 2005. In January of 2006 the City Manager received a letter from a resident of the Little Walnut Creek Community stating the following:

“Where's the new sewer line we've been promised?”

“The City promised us the line down Northeast”


With the tunnel mining operation complete two months prior to the resident's letter, it was clear that the resident was unaware that the construction for the sewer line down Northeast Drive had already been completed. Clearly a sign that impacts to the community were kept to a minimum.

The project reached substantial completion in July of 2006 well within the projects fast track schedule. The project is ultimately a success with neighborhood acceptance and minimal impact to the community and the environment.

Document Type: Research Article

DOI: http://dx.doi.org/10.2175/193864706783763390

Publication date: January 1, 2006

More about this publication?
  • Proceedings of the Water Environment Federation is an archive of papers published in the proceedings of the annual Water Environment Federation® Technical Exhibition and Conference (WEFTEC® ) and specialty conferences held since the year 2000. These proceedings are not peer reviewed.

    WEF Members: Sign in (right panel) with your IngentaConnect user name and password to receive complimentary access.
  • Subscribe to this Title
  • Membership Information
  • About WEF Proceedings
  • WEFTEC Conference Information
  • ingentaconnect is not responsible for the content or availability of external websites

Tools

Favourites

Share Content

Access Key

Free Content
Free content
New Content
New content
Open Access Content
Open access content
Subscribed Content
Subscribed content
Free Trial Content
Free trial content
Cookie Policy
X
Cookie Policy
ingentaconnect website makes use of cookies so as to keep track of data that you have filled in. I am Happy with this Find out more