EVALUATION OF IMPROVEMENTS TO PROVIDE ENHANCED TREATMENT RELIABILITY FOR A 160 MGD DIRECT FILTRATION WATER TREATMENT PLANT

Buy Article:

$17.50 plus tax (Refund Policy)

Or sign up for a free trial

Abstract:

The City of Phoenix in Arizona is a large metropolitan city experiencing tremendous population growth. Because of increasing demands for potable water and decreasing excess capacity of existing plants, the City has studied alternatives for increasing available water production, including building new plants and increasing reliability at existing plants. As a result of the study, the City decided to implement a reliability improvement project at the Union Hills Water Treatment Plant (UHWTP), an existing 160 mgd direct filtration plant. The UHWTP historically has experienced raw water quality variations that have decreased the deliverable capacity of the plant. The objective of the improvements project is to increase the reliability of the plant to produce 160 mgd finished water production even during poor raw water quality events. This paper discusses the implementation of this project.

The improvements project components include: replacing the media and underdrains in 32 existing filters, installation of four new filters, retrofitting an existing large raw water impoundment with new inertial flocculators and a sedimentation basin (pretreatment facilities), expansion of an existing used water recovery system, installing new ancillary chemical feed facilities, and constructing new solids handling facilities. The improvements project incorporates several innovative components along with a “fast track” schedule required by the City for implementation. To speed the project delivery, the City preselected a “Construction Manager @ Risk (CM@Risk)” at the beginning of the project. The CM@Risk will provide design and constructability reviews while the Engineer prepares traditional 50%, 90% and 100% plans and specifications submittals. The improvements project work will be constructed in three phases to speed delivery.

Innovative process considerations for the improvements project include: installation of an oscillating sludge scraper system versus traditional circular or chain and flight sludge collectors, optimizing sludge handling procedures for disposal at an adjacent sludge injection site, and installation of mechanical dewatering system to process chemical sludge produced from enhanced coagulation operations.

Document Type: Research Article

DOI: https://doi.org/10.2175/193864703784292052

Publication date: 2003-01-01

More about this publication?
  • Proceedings of the Water Environment Federation is an archive of papers published in the proceedings of the annual Water Environment Federation® Technical Exhibition and Conference (WEFTEC® ) and specialty conferences held since the year 2000. These proceedings are not peer reviewed.

    WEF Members: Sign in (right panel) with your IngentaConnect user name and password to receive complimentary access.
  • Subscribe to this Title
  • Membership Information
  • About WEF Proceedings
  • WEFTEC Conference Information
  • Ingenta Connect is not responsible for the content or availability of external websites
  • Access Key
  • Free ContentFree content
  • Partial Free ContentPartial Free content
  • New ContentNew content
  • Open Access ContentOpen access content
  • Partial Open Access ContentPartial Open access content
  • Subscribed ContentSubscribed content
  • Partial Subscribed ContentPartial Subscribed content
  • Free Trial ContentFree trial content
Cookie Policy
X
Cookie Policy
Ingenta Connect website makes use of cookies so as to keep track of data that you have filled in. I am Happy with this Find out more